West End, Soho

West End, Soho

Client | Private
Role | Dilapidations
Contract Value | Undisclosed
Timescale | 4 weeks

West End, Soho

About the project

PBC were appointed to prepare a schedule of dilapidations for this 5th Floor West End Office, located in the heart of Soho, London.

With the tenancy coming to an end, PBC acted on behalf of the landlord for this 3,311 sq ft commercial space:

1nternal Repairing & Insuring (IRI) Lease –5th Floor Office, West End (3,311 sq ft)

Original Claim – £144,983.60 (£43.79 per sq ft) With an Agreed Settlement – £130,594.37 (£39.44 per sq ft)

Timescale: Settled within four weeks of formal service
Client: Private

PBC Soho Dilapidations

See further dilapidation case studies here, and get in touch with our Building Consultancy team to assist you further here.

Instruction

PBC were appointed to prepare a schedule of dilapidations for this 5th Floor West End Office, located in the heart of Soho, London.